Example run · Sustainable Future Lab

What a Sustainable Future Lab review shows you

A fixed example sitting on one paper, with chosen decisions and a ranking that swaps the first two items of the best order, reviewed by the same engine that reviews yours. It is not a buyer's result.

Question 9 cost you the most: 6 practice points.

You chose C, You recommend taking the guarantee cash and re-tendering to the runner-up with the stronger marine record, and the marks put it below A, You recommend arranging access with the administrator and paying six hundred thousand from the guarantee to complete and release the two line-ups, without singling out one skill.

69/100

8 of 12 decisions held up · 13 questions: 1 priority ranking + 12 decisions · Time not recorded

CaseStar practice score, not a firm’s verdict

Ranking 83.0 × 20% + decision quality 66.0 × 50% + fit to the situation 65.0 × 30% = 69.1.

The estate letter. You chose: You recommend taking the guarantee cash and re-tendering to the runner-up with the stronger marine record. Three point one million contributes to the price difference. This secures a preferred long-term supplier, but gives up the nearly completed units rather than resolving their release and title.

The stronger option was A: arranging access with the administrator and paying six hundred thousand from the guarantee to complete and release the two line-ups.

The practice model puts “Accept the grid connection capacity offer” first; you put “Open the statutory rostering consultation” first. Nearest hard date and the harshest failure mode — nine months of waiting if the offer lapses.

The strongest one-move correction: “Accept the grid connection capacity offer” belongs above “Open the statutory rostering consultation”.

Your ranking is one move from the model.

The practice model puts “Accept the grid connection capacity offer” first; you put “Open the statutory rostering consultation” first. Nearest hard date and the harshest failure mode — nine months of waiting if the offer lapses.

Preview only. Your submitted ranking stays unchanged.

Move “Accept the grid connection capacity offer” from 2 to 1.

  1. Move “Accept the grid connection capacity offer” from 2 to 1.

Your one fix

Question 9

Why start here? One decision change could add about 5.4 points; one ranking move could add about 3.4 points. Both estimates use your sitting’s 100-point practice score. For a different road, we estimate halfway between its lowest and highest possible scores. Your answers on that road are unknown.

What you did

You recommended taking the guarantee cash and re-tendering to the runner-up with the stronger marine record.

Three point one million contributes to the price difference.

This secures a preferred long-term supplier, but gives up the nearly completed units rather than resolving their release and title.

The runner-up quotes fourteen weeks and a nineteen per cent premium.

The guarantee covers most of it, and the eighty-per-cent-built line-ups are broken for parts in a receiver’s sale.

The stronger option

You recommend arranging access with the administrator and paying six hundred thousand from the guarantee to complete and release the two line-ups.

Confirm title and remaining factory checks in writing.

Using existing equipment, not a replacement, keeps the nine-week schedule lead.

The units leave the works on a Thursday under the administrator’s signature.

The guarantee covers the completion cost; the programme loses three weeks, not the fourteen the next bidder quoted.

Next timeBefore you commit, name the constraint in the scenario and check that your recommendation can meet it.

Week twenty-two. Norvent enters administration with both switchgear line-ups eighty per cent built. Escrow gives you title; the guarantee covers three point one million against four point four million exposed. The administrator wants the units retained. Litigating title would add six weeks to delivery.

69/100

Ranking 83.0 × 20% + decision quality 66.0 × 50% + fit to the situation 65.0 × 30% = 69.1.

8 of 12 decisions held up.

  • 8 of 12 decisions took a strongest option
  • Ranking: priorities recorded
  • Time not recorded

Your scenario decisions

  1. Question 2. The capacity offer

    RightYou recommend accepting the eight-megavolt-ampere offer this week and tendering for a microgrid that shapes demand rather than carries it: a quayside battery, controlled reefer loads, a berth schedule keeping two large calls apart. The connection becomes a design constraint, not a wait.

    Acceptance comes with a day to spare, and the tender asks bidders to serve an eleven-megavolt-ampere peak behind an eight-megavolt-ampere connection. Two of three say they can.

  2. Question 3. The federation’s letter

    You recommend pausing the gantry conversion until the industrial position is clear. Three hundred and ten members have told you where they stand; pressing on while a ballot is organised would risk the tender, the fund deadline and the council relationship.

    The pause is welcomed in the paper and read inside the federation as proof that a branch meeting of forty can stop the programme. The ballot proceeds anyway.

    Stronger option: You recommend tabling the rostering proposal this week and opening forty-five-day statutory consultation on the thirty-four affected gantry posts; discuss attendance figures privately with the branch secretary. The arithmetic supports continued dialogue, not trying to win a public argument over membership.

    The board as it stood when you chose
    FederationHarbour Workers’ Federation opposes gantry conversion and threatens a ballot.
    OperationsOperations wants conversion paused.
    PositionStatutory consultation opens this month; the programme team needs your response before it begins.

    You chose B, You recommend pausing the gantry conversion until the industrial position is clear, and the marks put it below A, You recommend tabling the rostering proposal this week and opening forty-five-day statutory consultation on the thirty-four affected gantry posts; discuss attendance figures privately with the branch secretary, without singling out one skill.

    The stronger option A: You recommend tabling the rostering proposal this week and opening forty-five-day statutory consultation on the thirty-four affected gantry posts; discuss attendance figures privately with the branch secretary

  3. Question 4. The ballot

    RightYou recommend issuing the tender on time with an industrial-relations annex: the ballot, its scope, the consultation opening on a named date, and where the risk sits in the contract. Bidders will price a disclosed risk; they walk away from one discovered at contract signature.

    All three bidders stay in. One prices a two per cent industrial-action contingency and says so openly, which turns out to be the cheapest honest number in the tender.

    Why it holds up: Whether to wait for a ballot to close depends on how long the tender can wait compared with the days the ballot takes.

  4. Question 5. The load table

    You recommend approving the existing table. Eight point six megavolt-amperes fits the connection with margin and matches the approved business case. Reopening sizing before Thursday risks debating the whole envelope. Keep those figures for the board even though vessel classes changed after the original survey.

    Sizing is approved on eight point six and copied into the tender, the fund claim and the board minutes. The figure survives every document it touches until a ship makes it untrue.

    Stronger option: You recommend restating the peak on the vessel classes calling today — about eleven point four megavolt-amperes — and telling the board the connection is a shaping problem, not a capacity problem. The battery and berth rules become what this tender actually buys.

    The board as it stood when you chose
    Boardboard approves connection sizing Thursday.
    Basisengineer supplies the feasibility study’s berth table, underpinning the business case.
    PositionLines A and C moved to larger vessels eighteen months ago; nobody refreshed the survey.

    You chose B, You recommend approving the existing table, and the marks put it below A, You recommend restating the peak on the vessel classes calling today — about eleven point four megavolt-amperes — and telling the board the connection is a shaping problem, not a capacity problem, without singling out one skill.

    The stronger option A: You recommend restating the peak on the vessel classes calling today — about eleven point four megavolt-amperes — and telling the board the connection is a shaping problem, not a capacity problem

  5. Question 6. The first cold ironing

    RightYou recommend telling the distribution operator today, before the monthly reconciliation surfaces it, and imposing a berth rule that no two large calls overlap until shaping capacity exists. Self-reporting costs one difficult call; being found by the operator’s own meter data costs the queue position.

    The operator’s engineer is blunt and then helpful, and offers a temporary import-limit scheme the port did not know existed. The second event never happens.

  6. Question 7. The clarification

    RightYou recommend an addendum to all three bidders stating the sixty-hertz duty, absorbing the ten-day slip and re-phasing the interim claim to the next window. A tender that lets one bidder win on an ambiguity produces a challenge, or a quay that cannot power two lines.

    The addendum goes out Friday; one bidder’s price rises nine per cent and it stays in. The interim claim moves to November, and nobody ever asks the port to explain the award.

    Why it holds up: Whether a question needs an addendum depends on whether the specification already answers it: read what it actually states.

  7. Question 8. The availability number

    RightYou recommend awarding to Norvent conditionally: require a parent-company guarantee and title to the switchgear as construction proceeds. Its price and design lead. The four-unit marine record and impaired division justify specific security before paying eleven per cent more for the next bidder’s whole package.

    Norvent’s parent signs the guarantee after nine days of argument and a two-week delay. The escrow clause costs forty thousand in legal fees, forgotten until week twenty-two.

  8. Question 9. The estate letter

    You recommend taking the guarantee cash and re-tendering to the runner-up with the stronger marine record. Three point one million contributes to the price difference. This secures a preferred long-term supplier, but gives up the nearly completed units rather than resolving their release and title.

    The runner-up quotes fourteen weeks and a nineteen per cent premium. The guarantee covers most of it, and the eighty-per-cent-built line-ups are broken for parts in a receiver’s sale.

    Stronger option: You recommend arranging access with the administrator and paying six hundred thousand from the guarantee to complete and release the two line-ups. Confirm title and remaining factory checks in writing. Using existing equipment, not a replacement, keeps the nine-week schedule lead.

    The board as it stood when you chose
    SwitchgearNorvent enters administration with both switchgear line-ups eighty per cent built.
    CoverEscrow gives you title; the guarantee covers three point one million against four point four million exposed.
    PositionLitigating title would add six weeks to delivery.

    You chose C, You recommend taking the guarantee cash and re-tendering to the runner-up with the stronger marine record, and the marks put it below A, You recommend arranging access with the administrator and paying six hundred thousand from the guarantee to complete and release the two line-ups, without singling out one skill.

    The stronger option A: You recommend arranging access with the administrator and paying six hundred thousand from the guarantee to complete and release the two line-ups

  9. Question 10. The fourteen-week gap

    RightYou recommend telling the fund now that Berth 4 will energise by March and asking to re-phase Berths 7 and 9, with the supplier failure documented. Funds re-phase scope quarterly; they do not forgive discovering in April that March was never possible.

    The fund re-phases without penalty and asks for the administrator’s correspondence, already in hand. Berth 4 energises in the second week of March with a fund officer on the quay.

    Why it holds up: Whether temporary equipment can rescue a deadline depends on whether the fund’s own guidance counts it: read what the guidance says.

  10. Question 11. The berth schedule

    You recommend handling the overlaps case by case at the operations desk, where the duty manager knows the vessels, the cargo and the tides. A published rule will be wrong in half the situations it meets; the port keeps more flexibility deciding each on its merits.

    The duty managers make fourteen defensible decisions and no two of them the same way. By week six the shipping lines have started comparing, over dinner, the answers each of them was given.

    Stronger option: You recommend publishing a curtailment rule before the quarter starts: where two large calls overlap, the higher hotel load keeps shore power and the other runs on auxiliary, with eight weeks’ notice and a tariff credit for the curtailed call.

    The board as it stood when you chose
    ServiceBerth 4 is live and the shaping battery is half installed.
    OverlapsOperations sends next quarter’s call list: Deciding fact: on fourteen dates two large vessels are alongside at once, and the connection cannot power both at full draw.
    Positionport’s published tariff promises shore power to any berthed vessel able to take it.

    You chose B, You recommend handling the overlaps case by case at the operations desk, where the duty manager knows the vessels, the cargo and the tides, and it fell short against the ringed fact: How much machinery an allocation needs depends on how often the conflict arises: read the count before writing a rule for it.

    The stronger option A: You recommend publishing a curtailment rule before the quarter starts: where two large calls overlap, the higher hotel load keeps shore power and the other runs on auxiliary, with eight weeks’ notice and a tariff credit for the curtailed call

  11. Question 12. The unwritten rule

    RightYou recommend writing the rule down this week, publishing the six weeks of decisions alongside it including the ones that look bad, and taking the complaint that follows. You also take the crane instruction to the federation yourself, in person.

    The published log makes for a bad week and a decisive one. The federation raises the crane instruction formally and settles it in one meeting, because you brought it rather than hid it.

  12. Question 13. The completion report

    RightYou recommend reporting one hundred and seventy metered connections, separately showing availability and explaining curtailment. Flag Berth 9’s temporary switchgear. The verifier receives meter data next month; disclose the delivery basis now so its later reconciliation uses the definition in your own report.

    The verifier queries nothing and closes the claim in three weeks. Your curtailment paragraph becomes the reason the fund’s next window asks every applicant for metered use.

    Why it holds up: A reported measure is whatever the fund defines it to be: read the definition before choosing which count to report.

Practice bank · checked 28 October 2026: 12 papers across 6 stories. The Lab draws from a set, so a story can return. Example run regenerated and checked 31 October 2026.

Independent CaseStar practice informed by candidate reports. Not McKinsey's software. Your invitation sets the real assessment; timings here are ours.

What comes next

Your practice score does not decide whether you advance. Even a high real-test decile does not promise an interview; follow your recruiter’s next steps.

Preparing for another firm?

Practise a BCG case interview. Follow the assessment named in your invitation; BCG assessment practice is currently unavailable here.

Explore Bain Sova and TestGorilla practice. Bain’s invitation names the platform; the configuration depends on your role and office.

Bain digital-assessment guidance · source recorded 9 September 2026. Invitation instructions take priority.

CaseStar is operated by Case Study Generator, a sole proprietorship registered with the Dutch Chamber of Commerce (KvK 90905431). Questions: support@casestar.io · Terms · Accessibility · Privacy